“EVTA: Earn Value Technique Analysis”:Sistema de control de coste basado en el valor aportado al avance del proyecto.Descripción de los Términos e interpretación de Earned Value Management 1.PV (BCWS) Planned Value: estimated value of the workplanned to be done.2.EV (BCWP) Earned Value: estimated value of the work accomplished.3.AC (ACWP) Actual Cost: actual cost incurred.4.BAC Budget at Completion: How much did you BUDGET for the TOTAL JOB? 5.EAC Estimate at Completion: current expected cost of the TOTAL project.6.ETC Estimate to Complete: From this point on, how much MORE do we expect it to cost to finish the job? 7.VAC Variance at Completion: How much over or under budget do we expect to be?
Referencias:
Fórmulas: 1.Cost Variance (CV) EV – AC NEGATIVE is over budget, POSITIVE is under budget 2.Schedule Variance (SV) EV – PV NEGATIVE is behind schedule, POSITIVE is ahead of schedule 3.Cost Performance Index (CPI) EV / AC I am [only] getting _____ cents out of every $1. 4.Schedule Performance Index (SPI) EV / PV I am [only] progressing at ___% of the rate originally planned. 5.Estimate At Completion (EAC) Note: There are many ways to calculate EAC. 1.BAC / CPI • Used if no variances from the BAC have occurred 2.AC + ETC • Actual plus a new estimate forremaining work. Used when original estimate was fundamentally flawed.
“EVTA: Earn Value Technique Analysis”:Sistema de control de coste basado en el valor aportado al avance del proyecto.Descripción de los Términos e interpretación de Earned Value Management 1.PV (BCWS) Planned Value: estimated value of the workplanned to be done.2.EV (BCWP) Earned Value: estimated value of the work accomplished.3.AC (ACWP) Actual Cost: actual cost incurred.4.BAC Budget at Completion: How much did you BUDGET for the TOTAL JOB? 5.EAC Estimate at Completion: current expected cost of the TOTAL project.6.ETC Estimate to Complete: From this point on, how much MORE do we expect it to cost to finish the job? 7.VAC Variance at Completion: How much over or under budget do we expect to be?
Referencias:
Fórmulas: 1.Cost Variance (CV) EV – AC NEGATIVE is over budget, POSITIVE is under budget 2.Schedule Variance (SV) EV – PV NEGATIVE is behind schedule, POSITIVE is ahead of schedule 3.Cost Performance Index (CPI) EV / AC I am [only] getting _____ cents out of every $1. 4.Schedule Performance Index (SPI) EV / PV I am [only] progressing at ___% of the rate originally planned. 5.Estimate At Completion (EAC) Note: There are many ways to calculate EAC. 1.BAC / CPI • Used if no variances from the BAC have occurred 2.AC + ETC • Actual plus a new estimate forremaining work. Used when original estimate was fundamentally flawed.